It has been a little while since our last update. As you can imagine, the end-of-year period was relatively quiet, and there was not a whole lot to report, but since last week, things have accelerated considerably.

On Thursday, January 14, we did a final walkthrough meeting with the architects and contractors, and after finalizing a few important layout details, the construction crew was on-site and looking very busy at 7:30 a.m. on Friday, January 15.

As we write, the workers are leveling the floor of the future gym, demoing a large staircase along with various smaller structures, and we can already see a lot of wall framing being put in place. Additionally, our stair provider is manufacturing the frame for the stadium seating and preparing the main internal private staircase to be installed later.

On our end, we have decided on the finishes of the gym floor and kitchen, and we are refining the details of the doors and lock systems. With the final layout on the ground, we made what we hope are the last significant alterations to the project.

The official end of the construction is scheduled for May 29, as the contractors have not discovered any unexpected issues. In the meantime, of course, we will keep you uninformed with regular updates, including progress pictures, through this newsletter.

You can find the previous newsletters here:

New Building Announcement: June 21, 2024
Building Update #1: October 8, 2024
Building Update #2: October 31, 2024
Building Update #3: November 19, 2024
Building Update #4: December 12, 2024